Project Schedule

 

Regular visits by our members in Krakow (in their spare time, of course) will take during the reconstruction of car #137. Most of the preliminary engineering work was completed on a voluntary basis by our own members – something we can be proud of. Reconstruction of car #137 will take place in several steps. The following pictures of our last project, car #144, give some details about these steps.

 

From March 2026:
Setting technical specifications, preliminary engineering, design of parts.

Projektfahrplan 01 TW144 TechnischeZeichnungen Foto 20200731 090405

 

December 2026 - March 2028:
Manufacturing of underframe and riveted frame parts.

Projektfahrplan 02 TW144 Unterrahmen Foto 20210720 143941

 

March 2028 – March 2029:
Building and completing of the wooden car body.

Projektfahrplan 03 TW144 hoelzenerWagenkasten Foto20211203 174737

 

October 2030 - March 2031:
Interior finishing and decoration.

Projektfahrplan 04 TW144 Inneneinrichtung Foto 20231014  101541

 

January 2030 - October 2031:
Electrical and wiring work.

Projektfahrplan 05 TW144 elektrischeAusstattung Foto 20230116 142914

 

January 2031 - December 2031:
Overhaul of the historic powered trucks.

Projektfahrplan 06 TW144 Untergestell Foto 20230310 122321

 

Winter 2031 / 2032:
Overhaul of the historic powered trucks.

Projektfahrplan 07 TW144 Praesentation IMG 0855